In early December another of the weekend workshops to design the Spit Master Plan was held at SeaWorld, with representatives from the community, business and community groups present. This time the focus was on pulling together outcomes of public consultation on the 72 Options.
The Master Plan team consulted the community via the website survey which was completed by 815 people, 1294 visitors to the pop-up stalls around the coast, 117 speaking events and 35 business briefing attendees. The impressive outcome was the consensus across all sectors of the commitment to protecting the green of The Spit. The highest interest was in the Top of the Spit and the Village Hub, while the lowest was the proposed ocean side cruise terminal. he water quality of the Marine Stadium was the highest concern.
Two additional studies have been undertaken into the Aboriginal Cultural Heritage and the Environment, Ecology and Bushfire Review and Constraints Assessment.